Step 3. Frame Section Assembly
Select two (2) column/eave sections, one (1) rafter/ridge section and lay them out as shown preparatory to frame assembly. (In each case, a swaged end should abut an open end.)

Install the first swaged end into the adjacent open end making sure you have a tight, snug fit between the two. Install four (4) #12 Tek screws.

Repeat above process until an entire frame assembly is completed as shown in Figure 4.

TEMPORARY SUPPORT OF FRAME UNITS AS INSTALLATION PROGRESSES IS RECOMMENDED.

 